The mechanical shaft power of the motor — NOT cooling capacity. Enter motor kW, not tonnage or kW of cooling
HVAC equipment datasheet — look for "Motor kW" or "Input Power kW". Mechanical engineer equipment schedule or vendor technical submittal
AHU motor: 5.5–55kW
Motor Efficiency
Efficiency of the electric motor. Tool calculates: Electrical kW = Shaft kW ÷ Motor Efficiency
Motor datasheet or IEC 60034-30 efficiency class tables. IE3 motors required in most countries. If unknown use 0.88
IE3: 0.88–0.93
Demand Factor
Proportion of HVAC running simultaneously at full load. Chillers rarely run at 100% — this accounts for part-load operation
CIBSE Guide K or project M&E specification. Chillers: 0.8–0.9. AHUs: 0.75–0.85. FCUs: 0.7
Chiller: 0.85 | AHU: 0.8
❄️ Important: For chillers enter the compressor motor kW (electrical input), not cooling capacity. Example: a 500kW cooling chiller typically has a 150–200kW compressor input. Check the chiller datasheet for "Compressor Input kW".
Shaft power rating of the motor or pump — the mechanical output power. Can be entered in kW, W or HP
Motor nameplate data, pump datasheet, mechanical equipment schedule or pump curve. Look for "Shaft Power kW" or "Motor Rating kW"
CHW pump: 5.5–22kW
Motor Efficiency
Efficiency of the electric motor. Formula: Electrical kW = Shaft kW ÷ Motor Efficiency
Motor nameplate, manufacturer datasheet or IEC 60034-30 standard efficiency tables. IE3 motors mandatory in most countries from 2023
IE3 motor: 0.88–0.95
Demand Factor
Proportion of motors running simultaneously at full load. Do NOT add standby pumps — they do not contribute to load
CIBSE Guide K Table 4.2. CHW pumps: 0.8. Fire pumps: 1.0 (must always be 100%). Standby: 0 — do not add
Duty pump: 0.8 | Fire: 1.0
⚙️ Standby equipment: Do NOT add standby pumps or standby fans to the load calculation. Only add duty equipment. Standby equipment does not contribute to electrical load as it only runs when the duty unit fails.
📊 Understanding the Results
Result
What it Means
How it is Used
Connected Load (kW)
Total rated power of ALL equipment assuming everything runs at 100% simultaneously — worst case maximum
Sizing individual circuit protective devices (MCBs) and cable sizes at equipment level
Design Load (kW)
Connected load multiplied by demand factors — the realistic expected maximum load at peak conditions
Sizing main LV switchboard, incoming supply cables and transformer
Total kVA
Design load with spare capacity added, divided by power factor. This is what the transformer and utility supply must provide
Transformer sizing (must be ≥ total kVA), utility capacity request, generator sizing
Current per Phase (A)
Current flowing in each phase. Formula: I = kVA × 1000 ÷ (√3 × V) for 3-phase
Sizing main incoming cable, main incomer switch and busbar rating
MCB/MCCB Rating
Recommended standard IEC breaker size = Current × 1.25 rounded up to next standard size
Starting point for main incomer protection. Verify with fault level and discrimination study
📋 Recommended Step-by-Step Workflow
Step 1 — Set Project Details
Enter project name, supply voltage (400V for Middle East/UK), select 3-phase, set power factor (0.85 default) and spare capacity (20% minimum per IEC).
Step 2 — Add Lighting Load
Use W/m² at early design stage or W per fitting at detailed design. Get floor areas from architectural plans. Use LED power densities from CIBSE Guide A.
Step 3 — Add Small Power
Count outlets from electrical drawing. Use client equipment schedule for specific loads. Apply demand factor 0.4–0.5 for general office outlets per CIBSE Guide K.
Step 4 — Add HVAC Loads
Get motor kW from mechanical engineer's equipment schedule or HVAC datasheets. Enter shaft kW and motor efficiency. Do NOT add standby equipment.
Step 5 — Add Mechanical & General
Add pumps, lifts, compressors from mechanical schedule. Add UPS, EV chargers under General. Fire pumps always use demand factor 1.0.
Step 6 — Review Results
Check Full Schedule tab for complete load list. Use kVA for transformer sizing. Use current (Amps) for main cable and incomer sizing. Check PF recommendation.